Many candidates desire to prepare their AACE International CCP exam with the help of only updated and relevant study material. But during their research, they usually waste most of their valuable time with information that is either not relevant or outdated. Study4Exam has a fantastic team of subject-matter experts that make sure you always get the most up-to-date preparatory material. Whenever there is a change in the syllabus of the Certified Cost Professional (CCP) Exam , our team of experts updates CCP questions and eliminates outdated questions. In this way, we save you money and time.

AACE International CCP Exam Sample Questions:

Q1.

Money is value Having money when you need it is very important Money can also be valuable when used wisely by knowing when to spend and when to conserve. Also. planning now for future expenses can be a plus to the company rather than a debit. There are several ways to capitalize money and spending. Basically, there is the single payment mothed that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capita1 recovery factor and also the compound amount factor and present worth factor. At this point, we can assume money is worth 10%.

Which of the following is not one of the requirements to form a contract?

Q2.

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

How does the project stand?

Q3.

After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

Is the percent complete stated by the contractor correct?

Q4.

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is a method for figuring estimate at completion (EAC)?

Q5.

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the schedule variance (SV)?

Solutions:
Question: 1 Answer: D
Question: 2 Answer: C
Question: 3 Answer: A
Question: 4 Answer: D
Question: 5 Answer: D