Many candidates desire to prepare their ISM INTE exam with the help of only updated and relevant study material. But during their research, they usually waste most of their valuable time with information that is either not relevant or outdated. Study4Exam has a fantastic team of subject-matter experts that make sure you always get the most up-to-date preparatory material. Whenever there is a change in the syllabus of the Supply Management Integration exam, our team of experts updates INTE questions and eliminates outdated questions. In this way, we save you money and time.

ISM INTE Exam Sample Questions:

Q1.

A company produces and distributes its products in the continental United States, mostly to customers located in metropolitan areas. The company conducts an ABC analysis to classify items, and determines that A and B items have variable demand, while C items have relatively stable demand. The logistics group wants to use this information to minimize transportation costs. Which of the following is the BEST combination of modes for the firm to use in order to minimize costs?

Q2.

A supplier of aircraft seating receives a forecast from a major aircraft manufacturer. The forecast information is considered confidential, and thus the supplier must sign a Non-Disclosure Agreement (NDA). Given this situation, which of the following is MOST likely to be protected by the NDA?

Q3.

XYZ, Inc. has experienced a significant increase in the number of expedited orders with a key supplier over the last few months. In this situation, XYZ should

Q4.

A company is expanding its production capability. A project manager is assigned to bring a team of stakeholders together to conduct an analysis of the situation and develop a plan. During the analysis, the project manager gains an understanding of what resources stakeholders are willing to commit, the stakeholders' expectations, and what the stakeholders have to gain from the project. This analysis is MOST likely to identify which of the following?

Q5.

XYZ, Inc. is implementing a new automated system in its distribution center. The supply manager is developing measures to evaluate the success of the automated system pilot. Which of the following is the BEST metric to measure overall success of the pilot7

Solutions:
Question: 1 Answer: D
Question: 2 Answer: C
Question: 3 Answer: D
Question: 4 Answer: A
Question: 5 Answer: A