1. Home
  2. PMI
  3. PMI-RMP Exam Questions

Free PMI-RMP Exam Questions - PMI PMI-RMP Exam

PMI PMI-RMP Exam

PMI Risk Management Professional

Total Questions: 203

PMI-RMP Exam - Prepare from Latest, Not Redundant Questions!

Many candidates desire to prepare their PMI-RMP exam with the help of only updated and relevant study material. But during their research, they usually waste most of their valuable time with information that is either not relevant or outdated. Study4Exam has a fantastic team of subject-matter experts that make sure you always get the most up-to-date preparatory material. Whenever there is a change in the syllabus of the PMI Risk Management Professional exam, our team of experts updates PMI-RMP questions and eliminates outdated questions. In this way, we save you money and time.

PMI PMI-RMP Exam Sample Questions:

Q1.

Harold is the project manager of a large project in his organization. He has been actively communicating and working with the project stakeholders. One of the outputs of the manage stakeholder expectations process can actually create new risk events for Harold's project. Which output of the manage stakeholder expectations process can create risks?

Q2.

You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?

Q3.

Lamont is the project manager of a project that has recently finished the final project deliverables. The project customer has signed off on the project deliverable and Lamont has a few administrative closure activities to complete. In the project, there were several large risks that could have wrecked the project but Lamont and his project team found some creative methods to resolve the risks without affecting the project costs or project end date. What should Lamont do with the risk responses he identified during the project's monitoring and controlling process?

Q4.

Courtney is the project manager for her organization. She is working with the project team to complete the qualitative risk analysis for her project. During the analysis Courtney encourages the project team to begin the grouping of identified risks by common causes. What is the primary advantage to group risks by common causes during qualitative risk analysis?

Q5.

In what portion of a project are risk and opportunities greatest and require intense planning and anticipation of risk events?

Solutions:
Question: 1 Answer: B
Question: 2 Answer: D
Question: 3 Answer: D
Question: 4 Answer: C
Question: 5 Answer: C
Disscuss PMI PMI-RMP Topics, Questions or Ask Anything Related

Currently there are no comments in this discussion, be the first to comment!