Many candidates desire to prepare their Scrum SPS exam with the help of only updated and relevant study material. But during their research, they usually waste most of their valuable time with information that is either not relevant or outdated. Study4Exam has a fantastic team of subject-matter experts that make sure you always get the most up-to-date preparatory material. Whenever there is a change in the syllabus of the Scaled Professional Scrum exam, our team of experts updates SPS questions and eliminates outdated questions. In this way, we save you money and time.

Scrum SPS Exam Sample Questions:

Q1.

Scenario B: Six Team Nexus with complex dependencies

A six team Nexus is developing a complex product, with different parts of the product that only

certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside

the Nexus that are required for some of the work. In past Sprints the Nexus encountered

challenges dealing with the many dependencies between Scrum Teams.

Which of the following two strategies would be most effective in dealing with their

dependencies?

(choose the best two answers)

Q2.

Who has overall responsibility for ensuring Nexus Sprint Retrospective occurs?

(choose the best answer)

Q3.

True or False: Scrum Teams must report back to the Nexus Integration Team right after their individual Daily Scrums.

Q4.

Scenario A: Nexus Sprint Review with Five Scrum Teams

There are five Scrum Teams working on a product. During the Nexus Sprint Review, the teams

present the results of the Sprint. After introductions, each team takes time to present their work

for inspection by individually showing the new features they have built. They are not using a

shared environment. The stakeholders do not provide much feedback. The event ends and

people filter out of the room.

If this pattern of Nexus Sprint Reviews continues for multiple Sprints, what may be the effects?

(choose the best two answers)

Q5.

From the list below, what is the most important concern for multiple Scrum Teams when they

are working from the same Product Backlog?

(choose the best answer)

Solutions:
Question: 1 Answer: A, C
Question: 2 Answer: C
Question: 3 Answer: B
Question: 4 Answer: B, D
Question: 5 Answer: B